As the former headteacher of St Peter’s C of E Primary School, Ardingly, I write to point out some inaccuracies in your report on page 36 of the August 11 Middy.

The new school building was indeed begun in 1986 by Hilton’s of Haywards Heath and they progressed well until the company went into receivership after the 46 weeks reported, with the roof and interior unfinished.

Work ceased for some months while WSCC sought a new builder to take over the work, much to the disappointment of the Year 6 pupils who had looked forward to the summer term in a brand new building.

The work recommenced after several months and was finally completed and ready to move into after the autumn half term holiday 1987.

It was delayed again for two weeks due to the great storm which had brought down power lines and blocked the lane to both old and new schools.

Finally, the school re-opened on 1st November 1987 to much relief and celebration by everyone from governors, staff, PTA and of course, the children.

Catherine Fletcher

The Welkin, Lindfield

__

Don’t miss out on all the latest breaking news where you live.

Here are four ways you can be sure you’ll be amongst the first to know what’s going on.

1) Make our website your homepage at www.midsussextimes.co.uk

2) Like our Facebook page at www.facebook.com/midsussextimes

3) Follow us on Twitter @midsussex_times

4) Register with us by clicking on ‘sign in’ (top right corner). You can then receive our daily newsletter AND add your point of view to stories that you read here.

And do share with your family and friends - so they don’t miss out!

The Mid Sussex Times - always the first with your local news.

Be part of it.